China's Engineering Marvel: Rotating a 30,000 Ton Bus Terminal

Reverbtime Magazine

  • 0
  • 185
Scroll Down For More

As written by Trstdly, Chinese engineers recently pulled off an incredible feat - rotating an entire 30,000 ton bus terminal building to make way for a high-speed rail project. This marvel of engineering required years of planning and preparation to smoothly slide the massive terminal nearly 300 meters to its new position. Let's explore this astonishing achievement in detail and how it exemplifies China's exceptional engineering capabilities.

The Houxi Bus Terminal located in Xiamen, Fujian Province is one of the largest long-distance bus stations in southeast China. Opened in 2015, the imposing station covers about 169,000 square feet and cost $39 million to construct.

The terminal building consists of a steel structure enclosing waiting areas, ticketing counters, luggage rooms, and shopping concourses. Its foundation involves 20-foot-deep concrete pilings embedded in the earth. Overall, the completed building weighs around 30,000 tons - equal to over 170 Boeing 737s!

In 2018, the Fujian provincial government approved a new high-speed railway project necessitating space where the bus terminal stood. Facing this dilemma, engineers proposed temporarily moving the entire massive terminal building rather than demolishing it.

Shifting the foundation alone would have been impossible. So engineers decided to rotate the finished building within its foundation footprint to free up the needed land. This required swiveling the structure 90 degrees so its narrower side became the new frontage.

Rotating a building weighing 30,000 tons required every inch to move 288 feet on a winding journey. The logistical complexities were immense. But through ingenious design and testing, engineers brought their audacious plan to reality.

 

The Innovative Engineering Behind the Feat

The core innovation enabling the bus terminal's rotation involved installing 546 hydraulic jacks under the structure. Controlled in coordinated sets, each jack could apply over 550 tons of synchronized lifting force.

The jacks were anchored deep beneath the terminal foundation into the bedrock. By perfectly calibrating the lifting force of each jack, engineers could essentially lift the entire terminal slightly off the ground and keep it suspended.

The other vital component was a temporary steel track installed surrounding the foundation. The track's curved rails provided a low-friction surface for the building to slowly glide on once lifted.

The jacks and rails allowed the terminal to be pushed incrementally each day without toppling. Moving such a colossal building required the utmost precision and planning.

Engineers used 3D modeling to simulate the terminal's center of mass and test jack placements. Lasers and sensors tracked the structure's micro-movements continuously, alerting if any tilting occurred.

Additionally, the jacks were divided into two sets controlled by separate computer systems for redundancy. One set would lift while the other reset, allowing smooth cyclic movement.

With the tracks and jacks in place, the powering of this choreography fell to the hydraulic system. 140 pumps generated fluid pressure for the jacks. Meanwhile, the system's 60 miles of pipes and hoses distributed forces seamlessly.

The entire hydraulic configuration involved cutting-edge German engineering, demonstrating the project's technical sophistication. When active, the system applied an awe-inspiring 100,000 tons of lifting force on the terminal - equal to 14 Eiffel Towers!

 

Meticulous Planning and Preparation

Executing such a monumental feat of engineering required years of studies, tests, and planning. Construction teams performed extensive soil surveys to determine optimal jack placements that would distribute the terminal's weight without sinking or cracking the foundation.

Engineers then constructed an intricate 3D model of the terminal and performed simulated rotations. This allowed fine-tuning jack positions and lifting power while identifying any weak structural points requiring reinforcement.

Next came months of trial runs. The crews practiced rotating a dummy building partially constructed on-site. This allowed testing and improving the hydraulic jack synchronization and control systems.

By the time the actual terminal rotation began, engineers had perfected the specialized equipment and calculations enabling smooth sliding. The trial runs also helped construction teams master working around the titanic moving terminal quickly and safely.

When the day finally arrived in 2018, the engineering world watched in awe as the four-year preparations culminated in the terminal's slow but steady 90-degree journey.

 

Steady Movement Defying Gravity

The bus terminal rotation involved using the jacks to lift the structure 4 feet off the foundation rails. The building was raised incrementally over multiple days to avoid instability from sudden upward force.

Once optimally elevated, the jacks began pushing the terminal forward according to digital commands. The opposing jack sets gently slid the massive building ahead meter by meter.

Laser guidance systems and sensors tracked any minor sinking or tilting automatically adjusting jacks to counteract it. This created a mesmerizing motion likened to the terminal "crawling" forward.

The jack's tireless cycle continued day and night. Incredibly, the system could relocate the terminal up to 20 meters per day - a space equal to 5 school buses end to end. This slow and steady velocity prevented structural buckling.

Nearby roads and a bus parking lot had to be temporarily closed to provide space. Adjacent shopping malls also shut down as the looming terminal crawled past.

Watching the gargantuan building seem to defy gravity and glide smoothly without collapsing was both unsettling and marvelous for observers. The sheer enormity of such controlled movement felt like magic.

 

Completion of an Unparalleled Feat

After 40 days of round-the-clock work, the terminal completed its journey. The structure now stood rotated 90 degrees within its original foundation.

The project set a New Guinness World Record for the heaviest building ever relocated. Moving the 30,000 ton structure proved over 600% more massive than the previous 5,000 ton record holder!

Post-relocation, the terminal required several months of inspection and restoration work costing $1.5 million. But no major structural damage occurred. Soon bus operations resumed seamlessly in the relocated terminal.

Meanwhile, the high-speed rail project proceeded rapidly across the vacated land. Had the terminal been demolished, the debris removal alone could have delayed construction by months.

In total, rotating the terminal to its new position rather than rebuilding cost around $7.5 million. The relatively thrifty solution showcased how Chinese engineers harness resourcefulness to tackle obstacles.

Related Posts
Comments 0
Leave A Comment